题目

A company manufactures a single product, M. Budgeted production output of product M during August is 200 units. Each unit of product M requires 6 labour hours for completion and PR Co anticipates 20 per cent idle time. Labour is paid at a rate of $7 per hour. What is the direct labour cost budget for August?

A

$6,720

B

$8,400

C

$10,080

D

$10,500

Chapter16Thebudgetaryprocess

                                                                                                         Hours

Active hours required for production = 200 x 6 hours =                     1,200

Allowance for idle time (20% of total time = 25% of active time)        300

Total hours to be paid for                                                                    1,500 

x $7 per hour

Direct labour cost budget                                                                    $10,500

多做几道

A company uses a standard absorption costing system. Last month budgeted production was 8,000 units and the standard fixed production overhead cost was $15 per unit. Actual production last month was 8,500 units and the actual fixed production overhead cost was $17 per unit.What was the total adverse fixed production overhead variance for last month?

A

$7,500

B

$16,000

C

$17,000

D

$24.500

A cost centre had an overhead absorption rate of $4.25 per machine hour, based on a budgeted activity level of 12,400 machine hours.In the period covered by the budget, actual machine hours worked were 2% more than the budgeted hours and the actual overhead expenditure incurred in the cost centre was $56,389.What was the total over or under absorption of overheads in the cost centre for the period?

A

$1,054 over absorbed

B

$2,635 under absorbed

C

$3,689 over absorbed

D

$3,689 under absorbed

Which of the following would help to explain a favourable direct labour efficiency variance?

(i) Employees were of a lower skill level than specified in the standard

(ii) Better quality material was easier to process

(iii) Suggestions for improved working methods were implemented during the period

A

(i), (ii) and (iii)

B

(i) and (ii) only

C

(ii) and (iii) only

D

(i) and(II) only

Which of the following statements is correct?

A

An adverse direct material cost variance will always be a combination of an adverse material price variance and an adverse material usage variance

B

An adverse direct material cost variance will always be a combination of an adverse material price variance and a favourable material usage variance

C

An adverse direct material cost variance can be a combination of a favourable material price variance and a favourable material usage variance

D

An adverse direct material cost variance can be a combination of a favourable material price variance and an adverse material usage variance

The following information relates to labour costs for the past month:

Budget                 Labour rate                      $10 per hour

                            Production time                15,000 hours

                           Time per unit                     3 hours

                           Production units                5,000 units 

Actual                Wages paid                       $176,000

                          Production                         5,500 units 

                        Total hours worked             14,000 hours

There was no idle time.

What were the labour rate and efficiency variances? 

A

Rate variance                 Efficiency variance

$26,000 Adverse           $25,000 Favourable

B

Rate variance                 Efficiency variance

 $26,000 Adverse           $10,000 Favourable

C

Rate variance                 Efficiency variance

 $36,000 Adverse           $2,500 Favourable

D

Rate variance                 Efficiency variance

 $36,000 Adverse           $25,000 Favourable