What was the total direct labour variance?

A

$6,000 Favourable

B

$20,000 Adverse

C

$22,000 Favourable

D

Nil

考点:Chapter21Performancemeasurement

The total direct labour variance can be found by comparing the flexed budget figures with the actual figures.

Budgeted labour cost per unit = $286,000/2,200=$130

Flexed for 2,000 units = $130 x 2,000=$260,000

Total direct labour variance

                                                                      $

Flexed direct labour cost                          260,000

but did cost                                               280,000

Total direct labour variance                      20,000(A)

多做几道

材料全屏
60

【单项选择题】

What was the adverse material price variance?

A

$1,000

B

$3,500

C

$7,500

D

$11,000

What was the favourable material usage variance?

A

$2,500

B

$4,000

C

$7,500

D

$10,000

材料全屏
62

【单项选择题】

What was the total direct materials variance?

A

Nil

B

$10,000 Adverse

C

$10,000 Favourable

D

$11,000 Adverse

What was the total direct labour variance?

A

$6,000 Favourable

B

$20,000 Adverse

C

$22,000 Favourable

D

Nil

What was the total direct variable overheads variance?

A

Nil

B

$12,000 Favourable

C

$12,000 Adverse

D

$11,000 Adverse