Az Ltd operates a shipbuilding business which specialises in constructing and modifying ships to order. In 2011, Az Ltd entered into an agreement with Bob to completely rebuild a ship to Bob's specification for a total contract price of £7 million. However, after completion, Bob informed Az Ltd that, due to the downturn in the world economy, he no longer needed the ship. Az Ltd had already expended £5 million on altering the ship, and immediately started an action against Bob for breach of contract.
However, in the week before the case was to be decided in the court, Az Ltd sold the ship for the same amount of money which they would have received from Bob.
28
【论述题】
State the purposes of awarding damages for breach of contract