A firm makes special assemblies to customers' orders and uses job costing.
The data for a period are:
Job number Job number Job number
AA10 BB15 CC20
$ $ $
Opening WIP 26,800 42,790 0
Material added in period 17,275 0 18,500
Labour for period 14,500 3,500 24,600
The budgeted overheads for the period were $126,000.
Job number BB15 was completed on the last day of the period.
【单项选择题】
What overhead should be added to job number CC20 for the period?
$65,157
$69,290
$72,761
$126,000