The following extract is taken from the production cost budget of S Co.
Production (units) 2,000 3,000
Production cost ($) 11,100 12,900
What is the budget cost allowance for an activity level of 4,000 units?
The following extract is taken from the production cost budget of S Co.
Production (units) 2,000 3,000
Production cost ($) 11,100 12,900
What is the budget cost allowance for an activity level of 4,000 units?
Units $
High activity 3,000 12,900
Low activity 2,000 11,100
Increase 1,000 1,800
Variable cost per unit =$1,800/1,000=$1.80 per unit
Fixed cost, substituting in high activity = $12,900 - (3,000 x $1.80) =$7,500
Budget cost allowance for 4,000 units: $
Variable cost (4,000 x $1.80) 7,200
Fixed cost 7,500
14,700
Option A is the variable cost allowance only and option B is the fixed cost allowance only. If you selected option C your variable cost per unit calculation was upside down ($1,000/1,800 instead of $1,800/1,000
多做几道
A company uses a standard absorption costing system. Last month budgeted production was 8,000 units and the standard fixed production overhead cost was $15 per unit. Actual production last month was 8,500 units and the actual fixed production overhead cost was $17 per unit.What was the total adverse fixed production overhead variance for last month?
A cost centre had an overhead absorption rate of $4.25 per machine hour, based on a budgeted activity level of 12,400 machine hours.In the period covered by the budget, actual machine hours worked were 2% more than the budgeted hours and the actual overhead expenditure incurred in the cost centre was $56,389.What was the total over or under absorption of overheads in the cost centre for the period?
Which of the following would help to explain a favourable direct labour efficiency variance?
(i) Employees were of a lower skill level than specified in the standard
(ii) Better quality material was easier to process
(iii) Suggestions for improved working methods were implemented during the period
Which of the following statements is correct?
The following information relates to labour costs for the past month:
Budget Labour rate $10 per hour
Production time 15,000 hours
Time per unit 3 hours
Production units 5,000 units
Actual Wages paid $176,000
Production 5,500 units
Total hours worked 14,000 hours
There was no idle time.
What were the labour rate and efficiency variances?
最新试题
该科目易错题
该题目相似题