(1)___________ are a (2) ___________ remedy designed to restore the injured party to the position they would have been in had the contract been (3) ___________ A loss outside the natural course of events will only be compensated if the (4) ___________circumstances are within the (5) ___________'s knowledge at the time of making the contract. In assessing the amount of damage it is assumed that the (6) ___________will (7) ___________ their loss. A contractual term designed as a (8) ___________ is (9) ___________ .
When anticipatory breach occurs, the injured party has two options. These are
(1) ____________________
(2) ____________________
Which of the following statements in relation to liquidated damages is correct?
Which of the following is true regarding injunctions?
Rescission is an equitable remedy, and where available, makes the contract voidable. There are a number of conditions attached to the award of rescission.
Which of the following is a condition that must be met for an award of rescission to be made?
For an order for specific performance to be made, which TWO of the following criteria must be met?
(1) Damages must be inadequate compensation
(2) Consideration must have passed between the parties
(3) The parties must both agree to the award
(4) The contract must require performance over a long period of time
Which of the following remedies for breach of contract involves the injured party claiming the value of the work they have done?
【论述题】
State the nature of Jane's letter to Elle.
State whether Elle's reply at the end of March had lapsed through the passing of time.
State whether Jane has a valid contract with Elle for the sale of the boat.